CONTRACT 4438C Amendment CLOSED Agreement No. 4438C
Agreement No. 4438C
THIRD AMENDMENT TO
AGREEMENT NO. 4438 BETWEEN
THE CITY OF EL SEGUNDO AND
NCM ENGINEERING CORPORATION
THIS THIRD AMENDMENT ("Amendment") is made and entered into this 1 I 1 day of January
2017, by and between the CITY OF EL SEGUNDO, a general law city and municipal
corporation existing under the laws of California ("CITY"), and NCM ENGINEERING
CORPORATION, a California corporation ("CONSULTANT"). The parties agree as follows:
I. Pursuant to Section 35 of Agreement No. 4438 ("Agreement"), Section 1.0 of the
Agreement is amended to read as follows:
"CONSIDERATION. As additional consideration, CITY agrees to pay
CONSULTANT for CONSULTANT's services a sum not to exceed forty-nine
thousand one hundred forty-six dollars ($49,146.00). CITY will pay this sum on the
basis of the hourly rates and cost reimbursement rates as specified in the attached
Exhibit"A",which is incorporated herein."
2. The Agreement is amended to extend the term to February 28, 2018. The Agreement
may be renewed upon mutual consent of the parties. CITY and CONSULTANT
intend for this Amendment to be retroactively effective beginning October 1, 2015.
3. The Agreement is amended to add the services set forth in Exhibit `B," which is
attached to this Amendment and incorporated by reference. In accordance with the
Agreement, CITY agrees to pay the total costs for all services listed in the attached
Exhibit in exchange for CONSULTANT's services.
4. This Amendment may be executed in any number or counterparts, each of which will
be an original, but all of which together constitutes one instrument executed on the
same date.
5. Except as modified by this Amendment, all other terms and conditions of the
Agreement, as amended, remain the same.
[SIGNATURES ON NEXT PAGE]
Agreement No. 4438C
Agreement No. 4438C
IN WITNESS WHEREOF the parties hereto have executed this Amendment the day and
year first hereinabove written.
(I I I EL i I J N D NC,'Y1,,(�N�61NI
e-
Olt N inienlo. CFO
City arlage.l'
,4 �
ATTEST:
z�,k �k Taxpayer ID No. 46-1487149
C
el,
APPROVED AS TO FORM: ...........
MIfor—tv
ChN Auurney
2
Agreement No. 4438C
Exhibit A Page 1
COST PROPOSAL
Project: Park Place Extension Projecta a e e t Support
Client: City of EI Segundo Consultant: NCM Engineering Corp
350 Main Street 22362 Gilberto
Suite 125
EI Segundo, CA 90245 Rancho Santa Margarita, CA 92688
ATTN: Lifan Xu, PE ATTN: William Nascimento, PE, SE
City Engineer
Project No. OHL_1301
Element: Project Management Support Prepared by: WN
Date: January 3, 2017
Proposed Services:
Provide On Call Project Management Support to City Engineer to coordinate with the railroads,Chevron,
utility companies,and analyze right of way acquistion to assist in advancing the project.
William Nascimento and Mark Gonzalez(the PSR PM and PE)of NCM shall primarily lead coodination on behalf
of the City with support by other NCM staff and subconsultants as appropriate.
OH Multiplier for Design Build Proposal: 273%
Manhour Estimate: Man Direct Billing Labor
Hours Rate Rate Cost
1 Project Manager 36 95.00 259.16 9,330
2 Senior Project/Bridge Engineer100 75.00 204.60 20,460
3 Project/Bridge Engineer 65.00 177.32
4 Design Engineer 53.00 144.58
5 Assistant Engineer 42.00 114.58
6 QC 85.00 231.88
7 Senior CAD Operator 48.00 130.94
8 CAD Operator 41.00 111.85
9 Clerical/Administrative 30.00 81.84
Total Cost+Fee 136 $29,790 (A)
Other Direct Costs:
Other Direct Costs (Billed at actual cost with receipts)
1 Reproduction
2 Copying $480
3 Plotting
4 Transportation/Travel $1,327
5 Special Deliveries $50
6 Computer
7 Subconsultants $17,500
Subtotal- ODC $19,357 (B)
Total Proposed Fee
A Total Amount $49,145 (C)=(A+B)
Agreement No. 4438C
Exhibit A Page 2
NCM Engineering Corp.
COST PROPOSAL
Project: Park Place Extension Project Management Support
Client: City of EI Segundo Date:January 3,2017
Element: Project Management Support Proj:OHL_1301
Labor Hoirs by Classification
1 2 3 4 5 6 7 8 9 Total Subtotal
PM Sr.PE PE DE Asst QC Sr.CAD CAD Or Subs Hours
e0 O N w M M
M U�o 0 eq M w Cq
I- v v o
m M ao
N N N
TASKS/SUBTASKS
Engineering Services ���� .. ....
1 Coordination 36 100 136 $29,790
3 0
4
5 Q
6
7
8
Total 36 100 V 136 $29,789.76
Agreement No. 4438C
Exhibit A Page 4
NCM Engineering Corp.
COST PROPOSAL
Project: Park Place Extension Project Management Support
Client: City of El Segundo Date: January 3,201
Element: Project Management Support Proj: OHL_1301
Ref# Description Unit AnIourtt Cost/Unit Total
1 Reproduction/Plotting
Number of Drawings(Half Size) Ea
Size of Drawings(Half Size) 1.5 Sq Ft
Size of Drawlns(Full Size) 6 Sq Ft
Sluel'ines(Full Size) Sets Sq Ft 0.15 /Sq Ft
Xerox(Full Size) Sets Sq Ft 0,50 /Sq Ft
Sepia transparency(Full Size) Sets Sq Ft 080 /Sq Ft
Contact Mylars(Full Size) Sets Sq Ft 1.90 /Sq Ft
Velnrunra(Full Size) Sets Sq Ft 0.95 /Sq Ft
Subtotal(l) V
2 Copying/Binding
Reports20 Ea 200 Sheets 0.12
/Sheet 480
Calculations Ea Sheets 0.12 /Sheet
Specifications Ea Sheets 0.12 /Sheet
Half Size Drawings Sets Sheets 0.45 /Sheet
Binding(reports) Ea Tot 2.5 Ea
L Subtotal(2) $480.00
3 Plotting
Plotting (Half Size) Sets Sheets 5.75 /Sheet
PI ttin ( ull Size) Sets Sheets 6.50 /Sheet
Subtotal
4 Transportation/Travel
Flight Persons Trips EA 418 EA/Round Ti
Rental Car 1 Day(s) EA Trip 5 Trips Total 45 EA Day 225
Hotel/Per Diem Days 150 EA Day
Personal Car(Milea,gle) 120 Miles Round Trip 17 Trip 0.540 $/mile 1,102
Subtotal (4) $1,326.60
5 Special Deliveries
Express Mail 2 Deliveries 1 Ea 25 $/EA 50
Special Delivery Ea Ea 55 V
Subtotal (5) $50.00 j
6 Computer Costs
Engineering Design Hr 8
CAD Hr 24
Subtotal(6)
7Subconsul'tants
Wilson&Co LS 7,500
Overland Pacific LS 5,000
00
Utility
Coordin
tthrounh 6 LS $l9 600
u)btotal Subs $17,�
( g ) 6.60
Agreement No. 4438C
EXHIBIT B
Park Place Extension Project
.
Engineering
& Design Services
SCOIT OF i S"
✓ Protection or potential relocation of utilities
1,0)4 1 within railroad right of way under railroad
".,� '�Vl ,ttlG 'dlllld'. 1 : .1. �I.1�lt 1iG' VII1 "1` j11, °ml 1, license agreements
✓ Fundamental construction sequencing
i.0 ✓ Maintenance Access
The NCM team will review any additional documents, ✓ Obtaining pertinent information from the
reports,and studies prepared during the environmental
phase. railroad to develop design documents
✓ Project schedule
Environmental reports prepared by Michael
Baker Task LI Deliverables:
Task 1.0 Deliverables:
✓ Meeting Attendance and Minutes as applicable
V Existing Document Review Summary ✓ Draft MOUs(3)
Memorandum ✓ Draft C&M Agreement
1.1 Railroad Coordination L2 Utility Relocation C'oauu9d6uIlettioQu
Coordinate with the Union Pacific Railroad(UPRR), Coordinate with Plains All American, West Basin
BNSF Railway Company(BNSF)and Chevron through Municipal Water District and ExxonMobil through the
the environmental phase with the goal of obtaining environmental phase with the goal of obtaining
consensus on the plan of action for each of the consensus on the plan of action for each of the
alternatives under consideration. Begin the coordination alternatives under consideration for environmental
process of the C&M Agreement with the UPRR and clearance. Prepare MOU for the each agency with the
BNSF. For UPRR,BNSF and Chevron prepare City as a road map for final design once a preferred
Memorandum of Understanding(MOU)for the City as a alternative is selected. The team will utilize the support
road map for final design once a preferred alternative is of William Johns of Utility Coordinating Inc. for our
selected. Coordination with the CPUC will not begin utility coordination efforts. The key items to coordinate
until the project is in the final design stage.The CPUC with the utility companies include:
Application for an Order to Construct cannot be
submitted until after an environmental document has ✓ Existing Utility Operations and impacts to
been certified and the project design is at a stage where Utility Companies during construction
the project is well defined—typically 65%design Task 1.2 Deliverables:
complete. ✓ Meeting Minutes Attendance and as applicable
The team will utilize the support of Larry Long of ✓ Draft MOUS(3)
Wilson and Company for our railroad coordination
efforts. The key items to coordinate with the railroads
include: 1.3 Right (of Way ("oordination
Based on the alternatives being evaluated for the
✓ Existing Rail Operations and impacts to Rail environmental phase,develop a comparative strategy for
Operations during construction R/W acquisition for alternatives under consideration
✓ Potential impacts to Rail served customers under the environmental phase.
✓ Temporary and permanent horizontal and
Task 1.3 Deliverables:
vertical clearances proposed from the existing ✓ Preliminary Project Right of Way Strategy
tracks
✓ Bridge overhead clearance
✓ Changes in drainage