71that the food preparation area does not require the installation of
grease interceptors, then this condition will not be required.
29. Construction activities must include a storm water pollution
prevention plan addressing non -storm water run -off, debris
removal, track -out and protection of storm water system.
30. Any diesel - powered generators must be approved by the Fire
Department, Environmental Safety Division, and provide for
secondary containment, placarding, spill detection and prevention.
Underground tanks require additional environmental monitoring
requirements.
31. The applicant must provide the Environmental Safety Division of
the El Segundo Fire Department an inventory of any and all
chemicals used for laundry, pool or house cleaning, emergency
generators or other devices.
32. The applicant, or designee, must contact Underground Service
Alert before digging or excavating.
33. Any demolition must be screened for asbestos and lead, with
proper notifications to South Coast Air Quality Management District
(SCAQMD).
Public Works Department Conditions
34. All onsite utilities including, without limitation, water, electricity, gas,
sewer and storm drains, must be installed underground. Contact
Southern California Edison for required service and underground
requirements (Mr. John Deng at (310) 783 - 9305).
35. Before the City issues a Certificate of Occupancy, the applicant
must ensure that all curb, gutters, asphalt and concrete pavement
and driveway aprons fronting 540 East Imperial Avenue and the
property frontage along Walnut Avenue will be replaced as required
by the Public Works Department.
36. Before the City issues a Certificate of Occupancy, all damaged or
off -grade curb, sidewalk and pavement must be removed and
replaced as required by the Public Works Department.
37. The applicant must secure any required encroachment permits
from the Public Works Department before commencing any work in
the public right -of -way.