22requires the developer to submit Form 7460 -1 (Notice of Proposed
Construction or Alternation) to the Federal Aviation Administration
(FAA) and adherence to all local, state, and federal regulations
would ensure that a safety hazard does not occur as a result of
the proposed project. Therefore, this impact would be less than
significant with the incorporation of mitigation measure MM
HAZ -3.
(3) Emergency Plans. Construction activities associated with
Option 1 or Option 2 could temporarily result in lane closures on
adjacent roadways that could interfere with emergency plans.
However, mitigation measure MM HAZ-4 would ensure that
construction of the proposed project would not impede emergency
evacuations that could occur within the City by requiring that
emergency response teams for the City of El Segundo, including
the ESPD and ESFD, are notified of lane closures during
construction activities in the project area and that one lane would
remain open at all times to provide adequate emergency access
to the site and surrounding neighborhoods. Therefore, this impact
would be less- than - significant with the incorporation of mitigation
measure MM HAZ -4.
b) Mitigations:
MM HAZA Before demolition and /or construction activities, the
proposed project site must be tested for asbestos and lead by a
licensed contractor. The contractor must follow all applicable local,
state, and federal codes and regulations related to the treatment,
handling, and disposal of asbestos and lead if the proposed
project requires asbestos and /or lead abatement.
MM HAZ -2 In the event that previously unknown or unidentified
soil and /or groundwater contamination that could present a threat
to human health or the environment is encountered during
construction at the project site, construction activities in the
immediate vicinity of the contamination must cease immediately. If
contamination is encountered, a Risk Management Plan must be
prepared and implemented that (1) identifies the contaminants of
concern and the potential risk each contaminant would pose to
human health and the environment during construction and post -
development and (2) describes measures to be taken to protect
workers and the public from exposure to potential site hazards.
Such measures could include a range of options, including,
without limitation, physical site controls during construction,
remediation, long -term monitoring, post - development
maintenance or access limitations, or some combination thereof.
Depending on the nature of contamination, if any, regulatory
agencies must be notified (e.g., El Segundo Fire Department). If
needed, a Site Health and Safety Plan that meets Occupational
Safety and Health Administration requirements must be prepared
and in place before commencement of work in any contaminated
area.