2024-09-17 CC Agenda Packet - ITEM D15 - ES Recreation Park Renovation ScheduleEl Segundo Recreation Park Renovation
SCHEDULE — Parallel schedule for both Task 1 (Teen Center and Teen Plaza Renovation and
Skatepark) and Task 2 (Replacement of George Brett Field and Softball Field)
SCHEMATIC DESIGN
Site visits - ongoing
Site investigations and surveys — ongoing
Staff and Stakeholder Workshop —TBD - October 17, or October 24
Submit 100% SD deliverable — November 1
Recreation Park Renovation Subcommittee — November 7
Recreation and Parks Commission — November 20
Present SD to City Council— December 3, 2024
DESIGN DEVELOPMENT-12 weeks (December— February 2025)
Submit materials selections for city review (Teen Center and Plaza only) — December 17
Submit 50% DD Package — January 8
Prepare Environmental Documentation —January 22
Submit LID report — January 22
City staff review — February 5
Submit 100% DD Package — February 25
CONSTRUCTION DOCUMENTS— 24 weeks (February - July 2025)
Submit 50% CD Package — April 8
City staff review—April29
Submit 90% CD Package for City staff review (Recreation, Parks and Library and Public Works) —
May 27
City staff review —June 10
Present to City Council —July 22
Revise and update package —August 8
Submit 90% CD Package to Building and Safety Division —August 12, 2025
PLAN CHECK AND PERMITTING — 6 weeks (August — September 2025)
Receive reviewer comments — August 26
Revise and update documents —September 16
Submit 100% CD agency permitting— September 23, 2025