CONTRACT 6629A Amendment CLOSEDAgreement No. 6629A
FIRST AMENDMENT TO
AGREEMENT NO. 6629 BETWEEN
THE CITY OF EL SEGUNDO AND
CORRAL CONSTRUCTION & DEVELOPMENT INC.
GM 23-04: BOBBYSOX FIELD RESTROOM REPAIR PROJECT
THIS FIRST AMENDMENT ("Amendment") is made and entered into this 91' day of August
2023, by and between CITY OF EL SEGUNDO, a general law city and municipal corporation
existing under the laws of California ("CITY"), and CORRAL CONSTRUCTION &
DEVELOPMENT INC. ("CONTRACTOR").
1. Pursuant to Section 18 of Agreement No. 6629 ("Agreement"), in addition to the
amount set forth in Section 1(C) of the Agreement, the City agrees to pay
CONTRACTOR an additional sum not to exceed Two Thousand, Nine Hundred Eighty
Dollars ($2,980) for CONTRACTOR's services at rates specified in Exhibit B. City
may adjust such amounts in accordance with the Agreement. The total amount of the
contract not to exceed $7,450.00
2. This Amendment may be executed in any number of counterparts, each of which will
be an original, but all of which together constitutes one instrument executed on the
same date.
3.. Except as modified by this Amendment, all other terms and conditions of Agreement
No. 6629 will remain the same.
[SIGNATURES ON NEXT PAGE]
1
Agreement No. 6629A
IN WITNESS WHEREOF the parties hereto have executed this Amendment the day and
year first hereinabove written.
CITY OF EL SEGUNDO,
Darrell George,
City Manager
TT'
Tracy'Weaver.
City Clerk
APPROVED AS TO FORM:
MARK D. HfN LEY City Attorney
By:
JoaquinI'a cex,
AssistantCity Attorney
2
CORRAL CONSTRUCTION &
DEVELOPMENT INC.
Name: ;oro
Title: PXtsidExT
Taxpayer ID No. 2 to' 3 Z SZ `7 `/ 5-
Contractor State 2 $ $ �S
License No.:
Contractor City Business
License No.: 31111440
EXHIBIT B
Agreement No. 6629A
Corral Constrruction.28805
5211 E. Washington Boulevard #2-122
Commerce, CA 90040
562 762-6632
corr l.constructioii alioo.co
August 2, 2023
Jorge Prado
City of El Segundo
Re: Bobbysox Field Water Repair (Kitchen/Lavatory)
Scope of Work
- Connect to existing water supply pipe at exterior of building. Run new copper water line on
outside of the building to location of Men's Room Lavatory, bore hole through exterior wall
into Men's restroom and install a new angle stop to connect Lavatory. Continue exposed
copper water piping into kitchen area and make a new connection at water heater.
Estimate Amount $2,980.00